Which of the following tools is used to identify potential events and contingencies for an implementation plan?
The correct answer is B. Process decision program chart. A Process Decision Program Chart (PDPC) is specifically designed to anticipate potential problems and map out contingencies before they occur during implementation - making it the right tool for proactively identifying "what could go wrong" and planning responses in advance…
Question
Which of the following tools is used to identify potential events and contingencies for an implementation plan?
Options
- APERT chart
- BProcess decision program chart
- CFishbone diagram
- DHouse of quality
How the community answered
(49 responses)- A2% (1)
- B90% (44)
- C6% (3)
- D2% (1)
Explanation
A Process Decision Program Chart (PDPC) is specifically designed to anticipate potential problems and map out contingencies before they occur during implementation - making it the right tool for proactively identifying "what could go wrong" and planning responses in advance.
Why the others are wrong:
- A. PERT chart - schedules tasks and estimates project timelines using dependencies; it plans when, not what-if.
- C. Fishbone diagram - analyzes root causes of a problem that has already happened, not future contingencies.
- D. House of quality - translates customer requirements into design specifications (a QFD tool); it's for product planning, not risk/contingency mapping.
Memory tip: Think of PDPC as a "what-if decision tree" - it branches out from each implementation step asking "what could go wrong here, and what's our backup?" The word decision in the name signals it's about choosing responses to potential events.