CSSBB · Question #444

Use this data to calculate the Z score. Average oF. 65, Standard Deviation: 3, Upper Spec Limit: 72

The correct answer is C. 2.33. See the full explanation below for the reasoning.

Measure Phase

Question

Use this data to calculate the Z score. Average oF. 65, Standard Deviation: 3, Upper Spec Limit: 72

Options

  • A0.27
  • B1.5
  • C2.33
  • D4.12

How the community answered

(17 responses)
  • A
    12% (2)
  • C
    82% (14)
  • D
    6% (1)

Topics

#Z score#process capability#specification limits#standard deviation