The primary objective in removal of waste is to improve the Order Production Cycle where the time from _________________ to the time of receipt of payment is compressed.

The correct answer is C. Receipt of an order. See the full explanation below for the reasoning.

Improve Phase

Question

The primary objective in removal of waste is to improve the Order Production Cycle where the time from _________________ to the time of receipt of payment is compressed.

Options

  • AShift start
  • BProduct development
  • CReceipt of an order
  • DNew fiscal year

How the community answered

(19 responses)
  • A
    5% (1)
  • B
    5% (1)
  • C
    74% (14)
  • D
    16% (3)

Topics

#order production cycle#lean principles#waste reduction#lead time