CSSBB · Question #345

Using this partial Z Table, how many units from a month's production run are expected to not satisfy customer requirements for the following process? Upper specification limit: 7.2 Lower…

The correct answer is C. 10. See the full explanation below for the reasoning.

Measure Phase

Question

Using this partial Z Table, how many units from a month’s production run are expected to not satisfy customer requirements for the following process? Upper specification limit: 7.2 Lower specification limit: 4.3 Mean of the process: 5.9 Standard Deviation: 0.65 Monthly production: 450 units

Options

  • A3
  • B7
  • C10
  • D12

How the community answered

(37 responses)
  • A
    11% (4)
  • B
    3% (1)
  • C
    84% (31)
  • D
    3% (1)

Topics

#Z table#normal distribution#defect estimation#process capability