CSSBB · Question #185
An example of a project metric would be:
The correct answer is D. all the above. See the full explanation below for the reasoning.
Measure Phase
Question
An example of a project metric would be:
Options
- Athe decrease in defect occurrence
- Bthe decrease in product cost
- Cthe decrease in cycle time
- Dall the above
How the community answered
(57 responses)- A7% (4)
- B4% (2)
- C14% (8)
- D75% (43)
Topics
#project metrics#defect reduction#cycle time#cost reduction