Which metric is most misleading at portfolio level?
The correct answer is C. Velocity. Velocity has no meaning beyond team context.
Agile Planning and Estimation
Question
Which metric is most misleading at portfolio level?
Options
- ACost variance
- BCustomer value
- CVelocity
- DLead time
How the community answered
(40 responses)- A15% (6)
- B8% (3)
- C73% (29)
- D5% (2)
Explanation
Velocity has no meaning beyond team context.