CSAPM · Question #144

Which risk often remains invisible in agile projects?

The correct answer is C. Opportunity cost. Delivering the wrong priorities is a silent risk.

Agile Planning and Estimation

Question

Which risk often remains invisible in agile projects?

Options

  • ATechnical debt
  • BCultural resistance
  • COpportunity cost
  • DSchedule delay

How the community answered

(28 responses)
  • A
    21% (6)
  • B
    4% (1)
  • C
    64% (18)
  • D
    11% (3)

Explanation

Delivering the wrong priorities is a silent risk.

Topics

#opportunity cost#invisible risk#risk management#agile projects