A security analyst is deploying a new application in the environment. The application needs to be integrated with several existing applications that contain SPI. Prior to the deployment, the analyst…

The correct answer is B. a business impact analysis. Before implementation, BIA needs to be conducted and particularly when dealing with Sensitive Personal information (SPI). Application stress testing can be conducted once you implement the application in a staging environment. Business impact analysis (BIA) is the process of…

Submitted by amina.ke· Mar 6, 2026Security Operations

Question

A security analyst is deploying a new application in the environment. The application needs to be integrated with several existing applications that contain SPI. Prior to the deployment, the analyst should conduct:

Options

  • Aa tabletop exercise
  • Ba business impact analysis
  • Ca PCI assessment
  • Dan application stress test.

How the community answered

(25 responses)
  • A
    16% (4)
  • B
    72% (18)
  • C
    4% (1)
  • D
    8% (2)

Explanation

Before implementation, BIA needs to be conducted and particularly when dealing with Sensitive Personal information (SPI). Application stress testing can be conducted once you implement the application in a staging environment. Business impact analysis (BIA) is the process of assessing what losses might occur for each threat scenario. For instance, if a roadway bridge crossing a local river is washed out by a flood and employees are unable to reach a business facility for five days, estimated costs to the organization need to be assessed for lost manpower and production. Impacts can be categorized in several ways, such as impacts on life and SAFETY, impacts on finance and REPUTATION, and impacts on PRIVACY.

Topics