AW Computing created new multi-tier service plans. The primary difference between the packages Is the length of the term. The company wants to capture start and end dates for each service plan sold…

The correct answer is D. Make a validation rule on the Opportunity Product object to require custom date fields based on. Make a validation rule on the Opportunity Product object to require custom date fields based on the product family is how the administrator should ensure the data is captured properly. A validation rule is a way to enforce data quality and integrity.

Extend Custom Objects and Applications

Question

AW Computing created new multi-tier service plans. The primary difference between the packages Is the length of the term. The company wants to capture start and end dates for each service plan sold, which can direr from the contract dates of the subscription. How should an administrator ensure the data is captured properly?

Options

  • ABuild a validation rule on the Opportunity object to require custom date fields based on the
  • BConfigure formula fields to reflect the close date of the opportunity.
  • CCreate a new price book for service plans with term lengths.
  • DMake a validation rule on the Opportunity Product object to require custom date fields based on

How the community answered

(34 responses)
  • A
    15% (5)
  • B
    6% (2)
  • C
    6% (2)
  • D
    74% (25)

Explanation

Make a validation rule on the Opportunity Product object to require custom date fields based on the product family is how the administrator should ensure the data is captured properly. A validation rule is a way to enforce data quality and integrity.

Topics

#validation rules#Opportunity Product#custom date fields#data capture