A prototype lot of a new design suspension spring underwent testing with these results: - Total hours accumulated: 12,000 - Number of Failures: 6 - Hours to failure: 202, 387, 461, 590, 723, 864…

The correct answer is C. 0.0005/hour. See the full explanation below for the reasoning.

Data Collection and Use

Question

A prototype lot of a new design suspension spring underwent testing with these results:

  • Total hours accumulated: 12,000
  • Number of Failures: 6
  • Hours to failure: 202, 387, 461, 590, 723, 864

What is the failure rate?

Options

  • A0.0018/hour
  • B0.0024/hour
  • C0.0005/hour
  • D0.0020/hour