A plastics plant operates 8 extruders producing plastic film. Production volume requirements cannot be met if less than 6 extruders are operating. There is a .30 probability that a machine stopping…

The correct answer is C. 0.5518. You've hit your weekly limit · resets 5am (America/New_York)

Data Collection and Use

Question

A plastics plant operates 8 extruders producing plastic film. Production volume requirements cannot be met if less than 6 extruders are operating. There is a .30 probability that a machine stopping malfunction will occur. What is the probability that 6 extruders can remain operating throughout the day?

Options

  • A0.5783
  • B0.4482
  • C0.5518
  • D0.8059

How the community answered

(41 responses)
  • A
    7% (3)
  • B
    2% (1)
  • C
    76% (31)
  • D
    15% (6)

Explanation

You've hit your weekly limit · resets 5am (America/New_York)