Question

An air handling system has a MTBF of 8000 hours, MTBMct of 120 hours, and MMT (mean maintenance action time) of 230 hours. Determine the potential availability.

Options

  • A0.9866.
  • B0.9852.
  • C0.9721.
  • D0.9575.