ASQ
CRE · Question #25
CRE Question #25: Real Exam Question with Answer & Explanation
The correct answer is B. 0.9852.. See the full explanation below for the reasoning.
Question
An air handling system has a MTBF of 8000 hours, MTBMct of 120 hours, and MMT (mean maintenance action time) of 230 hours. Determine the potential availability.
Options
- A0.9866.
- B0.9852.
- C0.9721.
- D0.9575.
Community Discussion
No community discussion yet for this question.