A project manager meets with a customer for initial discussions about an upcoming project. At the end of the meeting, the customer asks the project manager for a rough estimate of the project…
The correct answer is D. It's not accounting for potential project delays. You've hit your limit · resets 12:50am (America/New_York)
Define AI Project Strategy
Question
A project manager meets with a customer for initial discussions about an upcoming project. At the end of the meeting, the customer asks the project manager for a rough estimate of the project duration. Based on her experience with three similar projects, the project manager provides an estimate of 8-10 months. What's wrong with this timeframe?
Options
- AIt's underestimating the project timeline by 3 months
- BIt fits into a waterfall timeframe, but not an agile project timeframe
- CIt's not accounting for data preparation timelines
- DIt's not accounting for potential project delays
How the community answered
(25 responses)- A12% (3)
- B8% (2)
- C24% (6)
- D56% (14)
Explanation
You've hit your limit · resets 12:50am (America/New_York)
Topics
#project estimation#timeline planning#risk management#project scoping