nerdexam
PMI

CPMAI · Question #40

A project manager meets with a customer for initial discussions about an upcoming project. At the end of the meeting, the customer asks the project manager for a rough estimate of the project…

The correct answer is D. It's not accounting for potential project delays. You've hit your limit · resets 12:50am (America/New_York)

Define AI Project Strategy

Question

A project manager meets with a customer for initial discussions about an upcoming project. At the end of the meeting, the customer asks the project manager for a rough estimate of the project duration. Based on her experience with three similar projects, the project manager provides an estimate of 8-10 months. What's wrong with this timeframe?

Options

  • AIt's underestimating the project timeline by 3 months
  • BIt fits into a waterfall timeframe, but not an agile project timeframe
  • CIt's not accounting for data preparation timelines
  • DIt's not accounting for potential project delays

How the community answered

(25 responses)
  • A
    12% (3)
  • B
    8% (2)
  • C
    24% (6)
  • D
    56% (14)

Explanation

You've hit your limit · resets 12:50am (America/New_York)

Topics

#project estimation#timeline planning#risk management#project scoping

Community Discussion

No community discussion yet for this question.

Full CPMAI Practice