CPMAI · Question #54

CPMAI Question #54: Real Exam Question with Answer & Explanation

The correct answer is C. Run it as a hybrid approach and some phases are run separately while other phases are combined. See the full explanation below for the reasoning.

Question

An organization is to undertake a multi-pattern AI project. They want to build a robot that is able to roam the halls as well as converse with employees and answer basic questions. What is the best approach for handling this project?

Options

  • ARun each pattern as its own project, with their own CPMAI phase iterations, data requirements,
  • BRun each pattern in isolation, with separate teams
  • CRun it as a hybrid approach and some phases are run separately while other phases are combined
  • DRun it as one project, combining teams, data requirements, and project needs