nerdexam
Isaca

COBIT5 · Question #9

The enterprise goal titled "Optimization of Business Process Costs" is aligned to which balanced scorecard (BSC) dimension?

The correct answer is C. Internal. https://community.mis.temple.edu/mis5203sec001sp2019/files/2019/01/COBIT-2019-Framework- Introduction-and-Methodology_res_eng_1118.pdf (24)

COBIT 5 Principles

Question

The enterprise goal titled "Optimization of Business Process Costs" is aligned to which balanced scorecard (BSC) dimension?

Options

  • AGrowth
  • BCustomer
  • CInternal

How the community answered

(35 responses)
  • A
    9% (3)
  • B
    14% (5)
  • C
    77% (27)

Explanation

https://community.mis.temple.edu/mis5203sec001sp2019/files/2019/01/COBIT-2019-Framework- Introduction-and-Methodology_res_eng_1118.pdf (24)

Topics

#balanced scorecard#enterprise goals#process optimization#goals cascade

Community Discussion

No community discussion yet for this question.

Full COBIT5 Practice