Isaca
COBIT-2019 · Question #40
Which of the following MUST be done before an enterprise can determine performance measures for a process improvement initiative?
The correct answer is A. Perform a process risk assessment. See the full explanation below for the reasoning.
Question
Which of the following MUST be done before an enterprise can determine performance measures for a process improvement initiative?
Options
- APerform a process risk assessment
- BCalculate return on investment (ROI)
- CConduct a capabilities assessment
How the community answered
(48 responses)- A83% (40)
- B6% (3)
- C10% (5)
Community Discussion
No community discussion yet for this question.