Which of the following MUST be done before an enterprise can determine performance measures for a process improvement initiative?

The correct answer is A. Perform a process risk assessment. See the full explanation below for the reasoning.

Question

Which of the following MUST be done before an enterprise can determine performance measures for a process improvement initiative?

Options

  • APerform a process risk assessment
  • BCalculate return on investment (ROI)
  • CConduct a capabilities assessment

How the community answered

(48 responses)
  • A
    83% (40)
  • B
    6% (3)
  • C
    10% (5)