Isaca
COBIT-2019 · Question #39
Which of the following should be scheduled for completion FIRST when prioritizing improvement initiatives?
The correct answer is A. Initiatives that are easiest to achieve and will garner business benefits. See the full explanation below for the reasoning.
Question
Which of the following should be scheduled for completion FIRST when prioritizing improvement initiatives?
Options
- AInitiatives that are easiest to achieve and will garner business benefits
- BInitiatives that are the least expensive in order to lower risk due to failure
- CInitiatives with the lowest cost regardless of expected business value
How the community answered
(30 responses)- A73% (22)
- B10% (3)
- C17% (5)
Community Discussion
No community discussion yet for this question.