What Change Enablement component in the Implementation Life Cycle supports the defining of the target state?

The correct answer is B. Forming the implementation team. See the full explanation below for the reasoning.

Question

What Change Enablement component in the Implementation Life Cycle supports the defining of the target state?

Options

  • AOperating and using the new approaches
  • BForming the implementation team
  • CIdentifying the role players
  • DCommunicating outcome

How the community answered

(17 responses)
  • A
    6% (1)
  • B
    76% (13)
  • C
    6% (1)
  • D
    12% (2)

Community Discussion