Isaca
COBIT-2019 · Question #173
What Programme Management component in the implementation Life Cycle is linked to embedding the new approaches?
The correct answer is A. Realise benefits. See the full explanation below for the reasoning.
Question
What Programme Management component in the implementation Life Cycle is linked to embedding the new approaches?
Options
- ARealise benefits
- BReview effectiveness
- CPlan programme
- DExecute the plan
How the community answered
(39 responses)- A72% (28)
- B10% (4)
- C3% (1)
- D15% (6)
Community Discussion