COBIT-2019 · Question #113

What is the name of the Change Enablement life cycle Phase which supports Phase 4. What needs to be done?

The correct answer is A. Identify role players. See the full explanation below for the reasoning.

Question

What is the name of the Change Enablement life cycle Phase which supports Phase 4. What needs to be done?

Options

  • AIdentify role players
  • BDefine target state
  • CPlan program
  • DDefine problems and opportunities

How the community answered

(29 responses)
  • A
    79% (23)
  • B
    3% (1)
  • C
    10% (3)
  • D
    7% (2)