COBIT-2019 · Question #112
Which aspect relates to the COBIT 5 principle 'Meeting Stakeholder Needs?
The correct answer is B. Translates stakeholder requirements into strategy. See the full explanation below for the reasoning.
Question
Which aspect relates to the COBIT 5 principle 'Meeting Stakeholder Needs?
Options
- AAligns with the latest views on Governance
- BTranslates stakeholder requirements into strategy
- CProvides a simple architecture
- DDefines relationship between Governance and Management
How the community answered
(56 responses)- A5% (3)
- B82% (46)
- C11% (6)
- D2% (1)