CNX-001 · Question #20
A partner is migrating a client from on premises to a hybrid cloud. Given the following project status information, the initial project timeline estimates need to be revised: Which of the following do
The correct answer is D. WBS. The Work Breakdown Structure is where each project phase and its duration are documented in detail. Since the estimated timelines for discovery, design, implementation, and knowledge transfer have all slipped, you update the WBS to reflect the new, actual phase durations.
Question
A partner is migrating a client from on premises to a hybrid cloud. Given the following project status information, the initial project timeline estimates need to be revised:
Which of the following documents needs to be revised to best reflect the current status of the project?
Exhibit
Options
- ABIA
- BSLA
- CSOW
- DWBS
How the community answered
(20 responses)- A10% (2)
- C5% (1)
- D85% (17)
Explanation
The Work Breakdown Structure is where each project phase and its duration are documented in detail. Since the estimated timelines for discovery, design, implementation, and knowledge transfer have all slipped, you update the WBS to reflect the new, actual phase durations.
Topics
Community Discussion
No community discussion yet for this question.
