A partner is migrating a client from on premises to a hybrid cloud. Given the following project status information, the initial project timeline estimates need to be revised: Which of the following do

The correct answer is D. WBS. The Work Breakdown Structure is where each project phase and its duration are documented in detail. Since the estimated timelines for discovery, design, implementation, and knowledge transfer have all slipped, you update the WBS to reflect the new, actual phase durations.

Cloud Network Implementation

Question

A partner is migrating a client from on premises to a hybrid cloud. Given the following project status information, the initial project timeline estimates need to be revised:

Which of the following documents needs to be revised to best reflect the current status of the project?

Exhibit

CNX-001 question #20 exhibit

Options

  • ABIA
  • BSLA
  • CSOW
  • DWBS

How the community answered

(20 responses)
  • A
    10% (2)
  • C
    5% (1)
  • D
    85% (17)

Explanation

The Work Breakdown Structure is where each project phase and its duration are documented in detail. Since the estimated timelines for discovery, design, implementation, and knowledge transfer have all slipped, you update the WBS to reflect the new, actual phase durations.

Topics

#Project Management#Cloud Migration#Work Breakdown Structure (WBS)#Project Timelines