A team is frustrated by the difficulty of the project on which they're working, and has asked the sponsor to attend their next meeting. The sponsor should:
The correct answer is B. Attend with a clear vision of the importance of the project. See the full explanation below for the reasoning.
Question
A team is frustrated by the difficulty of the project on which they're working, and has asked the sponsor to attend their next meeting. The sponsor should:
Options
- ADecline, since the team needs to own the process.
- BAttend with a clear vision of the importance of the project.
- CTry to identify resisting forces before attending the meeting.
- DAttend and communicate a sense of urgency.
How the community answered
(34 responses)- A15% (5)
- B76% (26)
- C6% (2)
- D3% (1)