CLO-002 · Question #600
A project manager received the results of a code review for a software release and reviewed the changes with the client. The project manager now wants to deploy the release based on the granted…
The correct answer is B. Change management. Change management is the policy that governs how changes to systems, applications, or infrastructure are made in an organized and controlled manner. The project manager should consult the change management policy to ensure that the proper processes and procedures are followed…
Question
A project manager received the results of a code review for a software release and reviewed the changes with the client. The project manager now wants to deploy the release based on the granted approval. Which of the following policies should the project manager consult prior to the deployment?
Options
- AEvent management
- BChange management
- CAccount management
- DIncident management
How the community answered
(58 responses)- A10% (6)
- B81% (47)
- C5% (3)
- D3% (2)
Explanation
Change management is the policy that governs how changes to systems, applications, or infrastructure are made in an organized and controlled manner. The project manager should consult the change management policy to ensure that the proper processes and procedures are followed before deploying the release. This includes verifying approvals, testing, rollback plans, and ensuring that the deployment will not disrupt business operations.
Topics
Community Discussion
No community discussion yet for this question.