CLO-002 · Question #517
A business analyst is performing a qualitative risk analysis. During the analysis, it is confirmed that nothing will be done to address the risk. Which of the following BEST describes the risk…
The correct answer is A. Acceptance. See the full explanation below for the reasoning.
Question
A business analyst is performing a qualitative risk analysis. During the analysis, it is confirmed that nothing will be done to address the risk. Which of the following BEST describes the risk response used in this situation?
Options
- AAcceptance
- BMitigation
- CTransference
- DAvoidance
How the community answered
(47 responses)- A74% (35)
- B9% (4)
- C13% (6)
- D4% (2)