Question
A company is planning to use cloud computing to extend the compute resources that will run a new resource-intensive application. A direct deployment to the cloud would cause unexpected billing. Which of the following must be generated while the application is running on-premises to predict the cloud budget for this project better?
Options
- AProof or concept
- BBenchmark
- CBaseline
- DFeasibility study
How the community answered
(51 responses)- A12% (6)
- B4% (2)
- C76% (39)
- D8% (4)