A company is planning to use cloud computing to extend the compute resources that will run a new resource-intensive application. A direct deployment to the cloud would cause unexpected billing…

The correct answer is C. Baseline. See the full explanation below for the reasoning.

Question

A company is planning to use cloud computing to extend the compute resources that will run a new resource-intensive application. A direct deployment to the cloud would cause unexpected billing. Which of the following must be generated while the application is running on-premises to predict the cloud budget for this project better?

Options

  • AProof or concept
  • BBenchmark
  • CBaseline
  • DFeasibility study

How the community answered

(51 responses)
  • A
    12% (6)
  • B
    4% (2)
  • C
    76% (39)
  • D
    8% (4)