A project manager must inform the Chief Information Officer (CIO) of the additional resources necessary to migrate services to the cloud successfully. Which of the following cloud assessments would…
The correct answer is B. Gap analysis. See the full explanation below for the reasoning.
Question
A project manager must inform the Chief Information Officer (CIO) of the additional resources necessary to migrate services to the cloud successfully. Which of the following cloud assessments would be MOST appropriate to use for the recommendation?
Options
- AFeasibility study
- BGap analysis
- CFuture requirements
- DBaseline report
How the community answered
(43 responses)- A14% (6)
- B74% (32)
- C5% (2)
- D7% (3)
Community Discussion