Which of the following is a ninth step in Systems Design Life Cycle?
The correct answer is A. Conversion. Conversion is the process of changing the existing system to the new system. It involves transferring data, installing hardware and software, training users, and decommissioning the old system. Conversion is the ninth step in the Systems Design Life Cycle, according to the CITM
IT Project Management
Question
Which of the following is a ninth step in Systems Design Life Cycle?
Options
- AConversion
- BBuilding
- CSystem Analysis
- DOperations
How the community answered
(18 responses)- A89% (16)
- B6% (1)
- C6% (1)
Explanation
Conversion is the process of changing the existing system to the new system. It involves transferring data, installing hardware and software, training users, and decommissioning the old system. Conversion is the ninth step in the Systems Design Life Cycle, according to the CITM