nerdexam
(ISC)2(ISC)2

CISSP-ISSMP · Question #97

CISSP-ISSMP Question #97: Real Exam Question with Answer & Explanation

The correct answer is C: It depends on what the termination clause of the contract stipulates.. To make a payment or not to make it depends on what the termination clause of the contract Answer option D is incorrect. The termination clause of the contract is the best input for this Answer option A is incorrect. While the ZAS Corporation did not choose to terminate the contr

Security Leadership and Management

Question

Eric is the project manager of the NQQ Project and has hired the ZAS Corporation to complete part of the project work for Eric's organization. Due to a change request the ZAS Corporation is no longer needed on the project even though they have completed nearly all of the project work. Is Eric's organization liable to pay the ZAS Corporation for the work they have completed so far on the project?

Options

  • AYes, the ZAS Corporation did not choose to terminate the contract work.
  • BIt depends on what the outcome of a lawsuit will determine.
  • CIt depends on what the termination clause of the contract stipulates.
  • DNo, the ZAS Corporation did not complete all of the work.

Explanation

To make a payment or not to make it depends on what the termination clause of the contract Answer option D is incorrect. The termination clause of the contract is the best input for this Answer option A is incorrect. While the ZAS Corporation did not choose to terminate the contract work the contract terms may stipulate other terms for early termination. Answer option B is incorrect. There's no indication of a lawsuit yet. Guide), Fourth Edition, ISBN:9781933890517, Section 12.4.

Topics

#Contract Management#Termination Clauses#Vendor Management#Legal Liability

Community Discussion

No community discussion yet for this question.

Full CISSP-ISSMP PracticeBrowse All CISSP-ISSMP Questions