Security Leadership and Management
Question
Mark is the project manager of the NHQ project in Spartech Inc. The project has an asset valued at $195,000 and is subjected to an exposure factor of 35 percent. What will be the Single Loss Expectancy of the project?
Options
- A$92,600
- B$67,250
- C$68,250
- D$72,650
Unlock CISSP-ISSMP to see the answer
You've previewed enough free CISSP-ISSMP questions. Unlock CISSP-ISSMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Quantitative Risk Analysis#Single Loss Expectancy#Risk Calculation#Exposure Factor