CISSP-ISSMP · Question #71
Part of your change management plan details what should happen in the change control system for your project. Theresa, a junior project manager, asks what the configuration management activities are f
The correct answer is B. Configuration Item Costing. Configuration item cost is not a valid activity for configuration management. Cost changes are managed by the cost change control system; configuration management is concerned with changes to the features and functions of the project deliverables.
Question
Part of your change management plan details what should happen in the change control system for your project. Theresa, a junior project manager, asks what the configuration management activities are for scope changes. You tell her that all of the following are valid configuration management activities except for which one?
Options
- AConfiguration Verification and Auditing
- BConfiguration Item Costing
- CConfiguration Identification
- DConfiguration Status Accounting
How the community answered
(44 responses)- A2% (1)
- B89% (39)
- C7% (3)
- D2% (1)
Explanation
Configuration item cost is not a valid activity for configuration management. Cost changes are managed by the cost change control system; configuration management is concerned with changes to the features and functions of the project deliverables.
Topics
Community Discussion
No community discussion yet for this question.