Question
You are a project manager of a large construction project. Within the project you are working with several vendors to complete different phases of the construction. Your client has asked that you arrange for some of the materials a vendor is to install next week in the project to be changed. According to the change management plan what subsystem will need to manage this change request?
Options
- ACost
- BResources
- CContract
- DSchedule
Unlock CISSP-ISSMP to see the answer