nerdexam
(ISC)2

CISSP-ISSMP · Question #43

You are a project manager of a large construction project. Within the project you are working with several vendors to complete different phases of the construction. Your client has asked that you…

The correct answer is C. Contract. Because the vendor is completing the work the change request will need to move through the contract change control system. There are four change control systems in project management: scope, cost, schedule, and contract. If the scope change control were a choice, it would be a…

Security Leadership and Management

Question

You are a project manager of a large construction project. Within the project you are working with several vendors to complete different phases of the construction. Your client has asked that you arrange for some of the materials a vendor is to install next week in the project to be changed. According to the change management plan what subsystem will need to manage this change request?

Options

  • ACost
  • BResources
  • CContract
  • DSchedule

How the community answered

(38 responses)
  • A
    13% (5)
  • B
    3% (1)
  • C
    76% (29)
  • D
    8% (3)

Explanation

Because the vendor is completing the work the change request will need to move through the contract change control system. There are four change control systems in project management: scope, cost, schedule, and contract. If the scope change control were a choice, it would be a valid

Topics

#Change Management#Vendor Management#Contract Management#Procurement