Question
You are the project manager of the HJK project for your organization. You and the project team have created risk responses for many of the risk events in the project. A teaming agreement is an example of what risk response?
Options
- AMitigation
- BSharing
- CAcceptance
- DTransference
Unlock CISSP-ISSMP to see the answer
You've previewed enough free CISSP-ISSMP questions. Unlock CISSP-ISSMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Risk Management#Risk Response Strategies#Teaming Agreements#Project Risk