CISSP-ISSMP · Question #32
CISSP-ISSMP Question #32: Real Exam Question with Answer & Explanation
The correct answer is D: Configuration Management System. The change management system is comprised of several components that guide the change request through the process. When a change request is made that will affect the project scope. The Configuration Management System evaluates the change request and documents the features and fun
Question
What component of the change management system is responsible for evaluating, testing, and documenting changes created to the project scope?
Options
- AScope Verification
- BProject Management Information System
- CIntegrated Change Control
- DConfiguration Management System
Explanation
The change management system is comprised of several components that guide the change request through the process. When a change request is made that will affect the project scope. The Configuration Management System evaluates the change request and documents the features and functions of the change on the project scope.
Topics
Community Discussion
No community discussion yet for this question.