CISSP-ISSMP · Question #20
You are the project manager of the HJK Project for your organization. You and the project team have created risk responses for many of the risk events in the project. Where should you document the…
The correct answer is C. Risk register. Risks and the corresponding responses are documented in the risk register for the project. Risk register is a document that contains the results of the qualitative risk analysis, quantitative risk analysis, and risk response planning. Description, category, cause, probability…
Question
You are the project manager of the HJK Project for your organization. You and the project team have created risk responses for many of the risk events in the project. Where should you document the proposed responses and the current status of all identified risks?
Options
- ARisk management plan
- BLessons learned documentation
- CRisk register
- DStakeholder management strategy
How the community answered
(14 responses)- C93% (13)
- D7% (1)
Explanation
Risks and the corresponding responses are documented in the risk register for the project. Risk register is a document that contains the results of the qualitative risk analysis, quantitative risk analysis, and risk response planning. Description, category, cause, probability of occurring, impact on objectives, proposed responses, owner, and the current status of all identified risks are put in the risk register. Answer option B is incorrect. The outcome of risk events and the corresponding risk responses may be documented in the project's lessons learned documented, but the best answer is to document the risk responses as part of the risk register. Answer option A is incorrect. The risk management plan defines how risks will be identified and analyzed, the available responses, and the monitoring and controlling of the risk events. The actual risk responses are included in the risk register. Answer option D is incorrect. The stakeholder management strategy defines how stakeholders and their threats, perceived threats, opinions, and influence over the project objectives will be addressed and managed.
Topics
Community Discussion