In which of the following types of tests are the disaster recovery checklists distributed to the members of disaster recovery team and asked to review the assigned checklist?

The correct answer is D. Checklist test. Checklist Test (D) is the simplest and most foundational DR test type - team members receive their assigned checklists and review them for completeness and accuracy, without any systems being activated or interrupted. This is purely a paper-based exercise to ensure everyone…

Architect for Governance, Risk, and Compliance

Question

In which of the following types of tests are the disaster recovery checklists distributed to the members of disaster recovery team and asked to review the assigned checklist?

Options

  • AParallel test
  • BSimulation test
  • CFull-interruption test
  • DChecklist test

How the community answered

(42 responses)
  • B
    2% (1)
  • C
    5% (2)
  • D
    93% (39)

Explanation

Checklist Test (D) is the simplest and most foundational DR test type - team members receive their assigned checklists and review them for completeness and accuracy, without any systems being activated or interrupted. This is purely a paper-based exercise to ensure everyone knows their responsibilities.

Why the distractors are wrong:

  • Parallel Test (A): Both the primary and backup systems run simultaneously to validate the backup can handle the load - actual systems are involved.
  • Simulation Test (B): The team acts out a disaster scenario in a realistic drill, but without switching over real production systems.
  • Full-Interruption Test (C): The most disruptive type - primary systems are actually shut down and operations fully transfer to the recovery site.

Memory tip: Think of the DR test types as a spectrum of disruption: Checklist → Walkthrough → Simulation → Parallel → Full-Interruption. The Checklist test is at the zero-disruption end - it's just reading paperwork, no systems touched.