In a large organization, it is MOST important that disaster recovery and business continuity plans:

The correct answer is A. are one integrated plan. Having one integrated plan ensures that disaster recovery (DR) and business continuity (BCP) activities are coordinated and do not conflict during an actual event. In a large organization, disjointed plans can cause confusion, duplication, or gaps in response. Testing them…

Submitted by devops_kid· Apr 18, 2026Information Security Program Development and Management

Question

In a large organization, it is MOST important that disaster recovery and business continuity plans:

Options

  • Aare one integrated plan.
  • Bare tested separately.
  • Caddress all backup systems used.
  • Dintegrate all business functions.

How the community answered

(39 responses)
  • A
    92% (36)
  • B
    5% (2)
  • D
    3% (1)

Explanation

Having one integrated plan ensures that disaster recovery (DR) and business continuity (BCP) activities are coordinated and do not conflict during an actual event. In a large organization, disjointed plans can cause confusion, duplication, or gaps in response. Testing them separately (B) is a useful practice but not the most critical requirement. Addressing all backup systems (C) is a component of DR but too narrow in scope. Integrating all business functions (D) is an important goal but is a subset of what an integrated plan achieves. A single, unified plan ensures consistent command, communication, and sequencing across all recovery activities.

Topics

#Disaster Recovery Planning#Business Continuity Planning#Integrated Planning#Organizational Resilience