The PRIMARY objective of timely declaration of a disaster is to:

The correct answer is A. ensure the continuity of the organization's essential services. The primary objective of promptly declaring a disaster is to initiate the recovery process swiftly, ensuring essential business services resume and continue operation.

Submitted by certguy· Apr 18, 2026Incident Management

Question

The PRIMARY objective of timely declaration of a disaster is to:

Options

  • Aensure the continuity of the organization's essential services.
  • Bprotect critical physical assets from further loss.
  • Censure engagement of business management in the recovery process.
  • Dassess and correct disaster recovery process deficiencies.

How the community answered

(24 responses)
  • A
    88% (21)
  • B
    4% (1)
  • C
    8% (2)

Why each option

The primary objective of promptly declaring a disaster is to initiate the recovery process swiftly, ensuring essential business services resume and continue operation.

Aensure the continuity of the organization's essential services.Correct

Timely disaster declaration activates the disaster recovery plan, which is designed to minimize downtime and disruption to critical business functions. The immediate goal is to restore and maintain the organization's essential services, thus ensuring business continuity even during adverse events.

Bprotect critical physical assets from further loss.

Protecting critical physical assets from further loss is a component of disaster response, but the overarching primary objective of *declaring* a disaster is business continuity, which encompasses more than just physical assets.

Censure engagement of business management in the recovery process.

While engagement of business management is crucial, it is a means to an end; the ultimate objective is the restoration and continuity of services, not merely their engagement.

Dassess and correct disaster recovery process deficiencies.

Assessing and correcting disaster recovery process deficiencies is a post-incident activity (lessons learned), not the primary objective of the declaration itself.

Concept tested: Disaster recovery primary objective

Source: https://nvlpubs.nist.gov/nistpubs/Legacy/SP/nistspecialpublication800-34r1.pdf