Which of the following should be of GREATEST concern when creating a continuity plan for a legacy system installed over ten years ago?
The correct answer is B. The duration for system restoration is longer than the business can accept. The greatest concern when creating a continuity plan for a legacy system is the duration for system restoration. If the recovery time exceeds what the business can accept, it can severely disrupt operations, making it a critical factor to address in the continuity plan.
Question
Which of the following should be of GREATEST concern when creating a continuity plan for a legacy system installed over ten years ago?
Options
- AThe system manufacturer does not provide support for the system.
- BThe duration for system restoration is longer than the business can accept.
- CThe incident response team does not have technical documentation for the system.
- DThe most recent security patches have not been applied to the system.
How the community answered
(28 responses)- A21% (6)
- B57% (16)
- C14% (4)
- D7% (2)
Explanation
The greatest concern when creating a continuity plan for a legacy system is the duration for system restoration. If the recovery time exceeds what the business can accept, it can severely disrupt operations, making it a critical factor to address in the continuity plan.