CGRC · Question #721
You are the project manager of the NKJ Project for your company. The project's success or failure will have a significant impact on your organization's profitability for the coming year. Management…
The correct answer is C. Risk utility function. A low level of stakeholder tolerance for risk in a project is formally described by a risk utility function, which illustrates their willingness to accept or take on risk.
Question
You are the project manager of the NKJ Project for your company. The project's success or failure will have a significant impact on your organization's profitability for the coming year. Management has asked you to identify the risk events and communicate the event's probability and impact as early as possible in the project. Management wants to avoid risk events and needs to analyze the cost-benefits of each risk event in this project. What term is assigned to the low-level of stakeholder tolerance in this project? Response:
Options
- ARisk avoidance
- BMitigation-ready project management
- CRisk utility function
- DRisk-reward mentality
How the community answered
(31 responses)- A6% (2)
- B3% (1)
- C87% (27)
- D3% (1)
Why each option
A low level of stakeholder tolerance for risk in a project is formally described by a risk utility function, which illustrates their willingness to accept or take on risk.
Risk avoidance is a strategy to eliminate a risk event, not a term describing tolerance for risk.
Mitigation-ready project management is a descriptive phrase for a proactive approach, not a defined term for risk tolerance.
The term 'risk utility function' describes a stakeholder's willingness to accept or take on risk, or their preference regarding risk. A low level of stakeholder tolerance for risk indicates a risk-averse utility function, meaning they derive less satisfaction from potential gains if accompanied by high risk.
Risk-reward mentality describes the balance between potential gain and potential loss, but 'risk utility function' is the formal term for measuring an individual's specific tolerance or preference for risk.
Concept tested: Project risk tolerance terminology
Source: https://www.pmi.org/learning/library/project-risk-management-planning-process-9937
Topics
Community Discussion
No community discussion yet for this question.