CGRC · Question #513

Which of the following is not part of the contents of a PO&Ms? Response:

The correct answer is D. Rules of engagement. A Plan of Action and Milestones (PO&M) details the tasks required to address security weaknesses, but does not typically include rules of engagement.

Compliance Maintenance

Question

Which of the following is not part of the contents of a PO&Ms? Response:

Options

  • AScheduled completion date
  • BResources required
  • CRecommended actions and milestones
  • DRules of engagement

How the community answered

(42 responses)
  • A
    2% (1)
  • B
    5% (2)
  • D
    93% (39)

Why each option

A Plan of Action and Milestones (PO&M) details the tasks required to address security weaknesses, but does not typically include rules of engagement.

AScheduled completion date

A scheduled completion date is a critical component of a PO&M, providing a timeline for addressing identified weaknesses.

BResources required

Resources required, such as funding, personnel, and equipment, are essential to include in a PO&M to ensure that remediation actions can be effectively implemented.

CRecommended actions and milestones

Recommended actions and milestones are the core elements of a PO&M, outlining the specific steps to mitigate vulnerabilities and track progress.

DRules of engagementCorrect

Rules of engagement define the scope and conduct for activities like penetration testing or incident response, which are distinct from the contents of a PO&M that outlines corrective actions for identified vulnerabilities. A PO&M focuses on remediation tasks, timelines, and necessary resources to fix security deficiencies.

Concept tested: Contents of a Plan of Action and Milestones (PO&M)

Source: https://nvlpubs.nist.gov/nistpubs/SpecialPublications/NIST.SP.800-18r1.pdf