CGRC · Question #510
Which of the following describes residual risk as the risk remaining after risk mitigation has occurred? Response:
The correct answer is A. DIACAP. DIACAP, the Department of Defense Information Assurance Certification and Accreditation Process, explicitly defined residual risk as the risk remaining after risk mitigation measures have been applied.
Question
Which of the following describes residual risk as the risk remaining after risk mitigation has occurred? Response:
Options
- ADIACAP
- BISSO
- CSSAA
- DDAA
How the community answered
(25 responses)- A88% (22)
- B4% (1)
- C8% (2)
Why each option
DIACAP, the Department of Defense Information Assurance Certification and Accreditation Process, explicitly defined residual risk as the risk remaining after risk mitigation measures have been applied.
DIACAP, the predecessor to the RMF in the DoD, was a comprehensive process that included the concept of residual risk, recognizing that not all risks can be completely eliminated. It required documentation of the risk remaining after the implementation of security controls and mitigation activities.
ISSO (Information System Security Officer) is a role or position, not a framework or process that defines residual risk.
SSAA (System Security Authorization Agreement) was a document used within DIACAP to record the security posture, but DIACAP itself provided the definition of residual risk.
DAA (Designated Approving Authority) is an individual authorized to make authorization decisions, not a process or framework defining risk concepts.
Concept tested: DIACAP Residual Risk Concept
Source: https://www.disa.mil/resource-library/library/dod-information-assurance-certification-and-accreditation-process-diacap-handbook
Topics
Community Discussion