CGRC · Question #478

Which of the following components ensures that risks are examined for all new proposed change requests in the change control system? Response:

The correct answer is D. Integrated change control. Integrated change control is the project management component that ensures risks are thoroughly examined for all proposed change requests within the change control system.

Security and Privacy Governance, Risk Management, and Compliance Program

Question

Which of the following components ensures that risks are examined for all new proposed change requests in the change control system? Response:

Options

  • ARisk monitoring and control
  • BScope change control
  • CConfiguration management
  • DIntegrated change control

How the community answered

(37 responses)
  • A
    3% (1)
  • B
    5% (2)
  • C
    3% (1)
  • D
    89% (33)

Why each option

Integrated change control is the project management component that ensures risks are thoroughly examined for all proposed change requests within the change control system.

ARisk monitoring and control

Risk monitoring and control focuses on tracking identified risks and implementing responses, rather than the initial examination of risks for new change requests.

BScope change control

Scope change control manages changes specifically to the project scope, which is a subset of the broader integrated change control process that includes risk assessment.

CConfiguration management

Configuration management identifies, documents, and controls changes to the system's configuration items, which is related but not the primary component for examining risks of new proposed change requests comprehensively.

DIntegrated change controlCorrect

Integrated change control is the overarching process in project management that reviews all change requests, assesses their potential impact across all project aspects, including risks, and approves or rejects them. This component ensures a holistic view of proposed changes, preventing unintended consequences and maintaining project integrity by examining risks associated with each change.

Concept tested: Integrated change control

Source: www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Integrated Change Control#Risk Management#Change Management#System Changes

Community Discussion

No community discussion yet for this question.

Full CGRC Practice