You work as a project manager for SoftTech Inc. You are working with the project stakeholders to begin the qualitative risk analysis process. You will need all of the following as inputs to the qualit

The correct answer is C. Stakeholder register. The stakeholder register lists project stakeholders, which is used for identifying who to consult regarding risks, but it is not a direct input document for the qualitative risk analysis process itself.

Security and Privacy Governance, Risk Management, and Compliance Program

Question

You work as a project manager for SoftTech Inc. You are working with the project stakeholders to begin the qualitative risk analysis process. You will need all of the following as inputs to the qualitative risk analysis process except for which one? Response:

Options

  • ARisk management plan
  • BRisk register
  • CStakeholder register
  • DProject scope statement

How the community answered

(29 responses)
  • A
    3% (1)
  • B
    3% (1)
  • C
    86% (25)
  • D
    7% (2)

Why each option

The stakeholder register lists project stakeholders, which is used for identifying who to consult regarding risks, but it is not a direct input document for the qualitative risk analysis process itself.

ARisk management plan

The risk management plan provides guidance on how to perform risk management activities, including qualitative risk analysis, making it an essential input.

BRisk register

The risk register, initially populated with identified risks, is a primary input for recording and updating risk assessments during qualitative risk analysis.

CStakeholder registerCorrect

The stakeholder register primarily lists project stakeholders and their details, which is crucial for identifying who might be affected by risks or who can provide expert judgment, but the register itself is not a direct input document for assessing risk probability and impact during qualitative risk analysis. Inputs for qualitative risk analysis typically include the risk management plan, risk register (initial), and project scope statement.

DProject scope statement

The project scope statement provides details about the project's objectives and deliverables, which are critical for understanding the context and potential impact of risks.

Concept tested: Project risk management inputs

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Project Management#Risk Management#Qualitative Risk Analysis#Process Inputs

Community Discussion

No community discussion yet for this question.

Full CGRC Practice