CGRC · Question #395
A part of a project deals with the hardware work. As a project manager, you have decided to hire a company to deal with all hardware work on the project. Which type of risk response is this? Response:
The correct answer is D. Transference. Hiring an external company to handle specific project work, like hardware, means shifting the responsibility and associated risks to that third party.
Question
A part of a project deals with the hardware work. As a project manager, you have decided to hire a company to deal with all hardware work on the project. Which type of risk response is this? Response:
Options
- AAvoidance
- BMitigation
- CExploit
- DTransference
How the community answered
(40 responses)- A3% (1)
- B3% (1)
- C8% (3)
- D88% (35)
Why each option
Hiring an external company to handle specific project work, like hardware, means shifting the responsibility and associated risks to that third party.
Avoidance is eliminating the risk by changing the project plan to remove the cause of the risk.
Mitigation is reducing the probability or impact of a risk event to an acceptable threshold.
Exploit is a strategy for opportunities (positive risks) where actions are taken to ensure the opportunity occurs and benefits are realized.
Transference, or sharing, is a risk response strategy where the project team shifts the responsibility for managing the risk, and the impact of the risk, to a third party. By hiring another company for hardware work, the project manager transfers the risks associated with that work to the external vendor.
Concept tested: Project risk response strategies (transference)