The amount of risk that an organization is willing to accept can be referred to as: Response:

The correct answer is D. Risk tolerance level. The amount of risk that an organization is willing to accept to achieve its objectives is known as its risk tolerance level. This level guides decision-making in risk management strategies.

Security and Privacy Governance, Risk Management, and Compliance Program

Question

The amount of risk that an organization is willing to accept can be referred to as:

Response:

Options

  • ARisk analysis
  • BRisk mitigation
  • CResidual risk
  • DRisk tolerance level

How the community answered

(15 responses)
  • A
    7% (1)
  • C
    7% (1)
  • D
    87% (13)

Why each option

The amount of risk that an organization is willing to accept to achieve its objectives is known as its risk tolerance level. This level guides decision-making in risk management strategies.

ARisk analysis

Risk analysis is the process of identifying, assessing, and evaluating risks, not the predefined amount of risk an organization is willing to bear.

BRisk mitigation

Risk mitigation refers to actions taken to reduce the likelihood or impact of a risk, not the level of risk considered acceptable.

CResidual risk

Residual risk is the risk that remains after all mitigation efforts have been applied, which may or may not be within the acceptable tolerance level.

DRisk tolerance levelCorrect

The risk tolerance level represents the specific amount of risk an organization is prepared to accept for a given risk or class of risks, aligning with its overall risk appetite and strategic objectives.

Concept tested: Risk tolerance and appetite

Source: https://www.nist.gov/glossary/risk-tolerance

Topics

#risk tolerance#risk management#risk acceptance