CGRC · Question #187

You are the project manager of the NHH project for your company. You have completed the first round of risk management planning and have created four outputs of the risk response planning process…

The correct answer is D. Organizational process assets updates. In project management, specifically risk response planning, outputs typically include updates to project documents like the risk register and contract decisions, but not direct updates to organizational process assets.

Security and Privacy Governance, Risk Management, and Compliance Program

Question

You are the project manager of the NHH project for your company. You have completed the first round of risk management planning and have created four outputs of the risk response planning process. Which one of the following is NOT an output of the risk response planning? Response:

Options

  • ARisk-related contract decisions
  • BProject document updates
  • CRisk register updates
  • DOrganizational process assets updates

How the community answered

(28 responses)
  • C
    4% (1)
  • D
    96% (27)

Why each option

In project management, specifically risk response planning, outputs typically include updates to project documents like the risk register and contract decisions, but not direct updates to organizational process assets.

ARisk-related contract decisions

Risk-related contract decisions are a direct output of risk response planning, especially when risk transference strategies involve external parties and contracts.

BProject document updates

Project document updates, such as updates to the project management plan, schedule, or cost baselines, are a common and expected output when risk responses impact various aspects of the project.

CRisk register updates

Risk register updates are a primary output of risk response planning, as identified risks are assigned owners, response strategies, and contingency plans, which are all recorded in the risk register.

DOrganizational process assets updatesCorrect

Organizational process assets (OPAs) are inputs to many project management processes, representing the organization's knowledge base and procedures. While project knowledge might eventually update OPAs over time or upon project closure, "Organizational process assets updates" is not a direct, immediate, and common output of the "Plan Risk Responses" process as defined by project management methodologies like PMBOK.

Concept tested: Project Management - Plan Risk Responses outputs (PMBOK)

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Risk Management Process#Risk Response Planning#Project Management Outputs