nerdexam
(ISC)2

CGRC · Question #131

There are five inputs to the quantitative risk analysis process. Which one of the following is NOT an input to the perform quantitative risk analysis process? Response:

The correct answer is D. Enterprise environmental factors. This question asks to identify which item is not an input to the Perform Quantitative Risk Analysis process according to project management methodologies. Enterprise environmental factors are generally considered constraints or influences, not direct inputs for this specific…

Security and Privacy Governance, Risk Management, and Compliance Program

Question

There are five inputs to the quantitative risk analysis process. Which one of the following is NOT an input to the perform quantitative risk analysis process? Response:

Options

  • ARisk register
  • BCost management plan
  • CRisk management plan
  • DEnterprise environmental factors

How the community answered

(33 responses)
  • A
    3% (1)
  • C
    9% (3)
  • D
    88% (29)

Why each option

This question asks to identify which item is not an input to the Perform Quantitative Risk Analysis process according to project management methodologies. Enterprise environmental factors are generally considered constraints or influences, not direct inputs for this specific process.

ARisk register

The risk register is a primary input, containing identified risks and their attributes, which are crucial for quantitative analysis.

BCost management plan

The cost management plan provides guidance on how project costs, including those related to risk, will be planned, structured, and controlled, making it a relevant input for cost-related risk analysis.

CRisk management plan

The risk management plan outlines how risk management activities will be performed on the project, including the methodologies and tools for quantitative analysis, making it an essential input.

DEnterprise environmental factorsCorrect

Enterprise environmental factors (EEFs) are conditions, not under the control of the project team, that influence, constrain, or direct the project. While EEFs influence how quantitative risk analysis is performed, they are not typically listed as a direct input document or data for the quantitative calculations themselves.

Concept tested: Project Risk Management Inputs

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Quantitative Risk Analysis#Risk Management Process#Process Inputs#Enterprise Environmental Factors

Community Discussion

No community discussion yet for this question.

Full CGRC Practice