CGEIT · Question #557
When conducting a risk assessment in support of a new regulatory requirement, the IT risk committee should FIRST consider the:
The correct answer is C. risk profile of the enterprise. When initiating a risk assessment for a new regulatory requirement, the IT risk committee should first consider the enterprise's overall risk profile to contextualize and prioritize potential impacts and exposures.
Question
When conducting a risk assessment in support of a new regulatory requirement, the IT risk committee should FIRST consider the:
Options
- Acost burden to achieve compliance.
- Breadiness of IT systems to address the risk.
- Crisk profile of the enterprise.
- Ddisruption to normal business operations.
How the community answered
(33 responses)- A3% (1)
- C94% (31)
- D3% (1)
Why each option
When initiating a risk assessment for a new regulatory requirement, the IT risk committee should first consider the enterprise's overall risk profile to contextualize and prioritize potential impacts and exposures.
Cost burden is an important factor, but it is typically assessed after understanding the risks and necessary compliance measures, not as the first step.
Readiness of IT systems is a detailed assessment component that follows the initial understanding of the overall risk context and regulatory impact.
The enterprise's existing risk profile provides a holistic view of its current risk appetite, major threats, vulnerabilities, and controls. Understanding this baseline allows the committee to effectively evaluate how the new regulatory requirement modifies or adds to the organization's overall risk posture and helps in prioritizing subsequent assessment steps.
Disruption to normal business operations is a potential consequence of non-compliance or remediation, which is evaluated after assessing the risk itself within the enterprise's profile.
Concept tested: Initial steps in regulatory risk assessment
Topics
Community Discussion
No community discussion yet for this question.