CGEIT · Question #532

In a large enterprise, which of the following is the BEST approach to enable effective communication to senior management regarding the project status for a strategic enterprise resource management…

The correct answer is D. A steering committee involving business and IT. For effective communication to senior management regarding a strategic enterprise resource management (ERM) system implementation, establishing a steering committee involving both business and IT is the best approach.

Submitted by amina.ke· Apr 18, 2026Governance of Enterprise IT

Question

In a large enterprise, which of the following is the BEST approach to enable effective communication to senior management regarding the project status for a strategic enterprise resource management system implementation?

Options

  • AProject management office with business and IT representatives
  • BWeekly project reports reviewed by business and IT management
  • CProject status updates on the intranet
  • DA steering committee involving business and IT

How the community answered

(40 responses)
  • A
    10% (4)
  • B
    3% (1)
  • C
    5% (2)
  • D
    83% (33)

Why each option

For effective communication to senior management regarding a strategic enterprise resource management (ERM) system implementation, establishing a steering committee involving both business and IT is the best approach.

AProject management office with business and IT representatives

A Project Management Office (PMO) coordinates and standardizes project management processes but typically operates at a functional level, not necessarily providing the direct, strategic communication channel to senior management that a steering committee offers for a specific high-impact project.

BWeekly project reports reviewed by business and IT management

Weekly project reports are important for detailed operational tracking, but they can overwhelm senior management and may lack the interactive discussion and direct strategic decision-making capabilities that a dedicated steering committee provides.

CProject status updates on the intranet

Project status updates on the intranet are a passive communication method that relies on senior management actively seeking out information, which is less effective for ensuring they are consistently informed and engaged in strategic decision-making for a critical project.

DA steering committee involving business and ITCorrect

A steering committee involving both business and IT senior management is the best approach for communicating strategic project status because it provides a dedicated forum for executive-level oversight, decision-making, and direct engagement. This ensures that strategic alignment, resource allocation, risk management, and overall project progress for a major initiative like an ERM system are regularly reviewed and guided by key stakeholders, fostering accountability and effective communication.

Concept tested: Project governance for strategic initiatives

Topics

#Project Governance#Steering Committee#Strategic Projects#Senior Management Communication